ISO 9001:2026 Clause 6.3 Planning of Changes: Requirements, Procedure and Examples

ISO Cloud Consulting editorial team
Planning of changes cycle under clause 6.3

Clause 6.3 of ISO 9001:2026 still requires changes to the quality management system to be carried out in a planned manner, but it adds three considerations to the four in the 2015 edition: how the change is communicated, how it is monitored, and how the results are reviewed. A change process that ends at approval no longer covers the clause.

What are the seven considerations?

Consideration Edition Question to answer
Purpose and potential consequences 2015 Why are we changing, and what could go wrong?
Integrity of the QMS 2015 Which processes, documents and records are affected?
Availability of resources 2015 Do we have the people, budget and time?
Responsibilities and authorities 2015 Who owns the change, and do roles need to change?
Communication 2026 Who needs to know, when, and how will we tell them?
Monitoring 2026 How will we know the change is going to plan?
Review of results 2026 Did the change achieve its purpose, and what did we learn?

This table summarises the clause in our own words. Check the exact wording in your copy of the standard.

Which changes does this apply to?

Clause 6.3 is about changes to the management system: introducing an ERP or eQMS, moving site, restructuring departments, outsourcing a process, changing a critical supplier, extending the certification scope. Design and development changes fall under 8.3.6 and production or service provision changes under 8.5.6. A good procedure explains the boundary so people know which route to use.

A simple change procedure

  1. Request. Anyone can raise a change request describing the change and its purpose.
  2. Assess. The process owner completes an impact assessment against the seven considerations.
  3. Approve. Top management or a delegated authority approves significant changes.
  4. Communicate. Issue the communication plan before implementation starts.
  5. Implement and monitor. Track actions in a change log with status and dates.
  6. Review. At a set point after go-live, review results against the purpose and record lessons learned.
  7. Report. Summarise open and closed changes at management review.

Worked examples

New ERP system

Consequences include data migration errors and loss of traceability. Monitoring is a weekly cutover checklist. The review of results, three months after go-live, checks order accuracy and on-time delivery against the period before the change.

Relocating a production line

QMS integrity items include revalidation, calibration after the move and updated work instructions. Communication covers customers who require notification of a site change. The review confirms first-pass yield has returned to the previous level.

Changing a key supplier

The assessment links to supplier evaluation under 8.4. Monitoring is incoming inspection results for the first ten deliveries. The review decides whether to reduce inspection to normal levels.

How to update your system

  • Add communication, monitoring and review fields to your change form.
  • Add a review date and review outcome to the change log.
  • Add planned changes and their results to the management review agenda.
  • Log the ISO 9001:2026 transition as change number one.

The Change Management Procedure and Log includes the 8-page procedure, form, log, review form and these three examples in editable Word and Excel.

Free sample

Get the free ISO 9001:2026 transition checklist

The one-page, 20-step checklist from gap analysis to transition audit. Real, unedited pages so you can judge the files before you buy.

You will also get occasional template updates and guidance. Unsubscribe any time. See our privacy policy.

Back to blog

Frequently asked questions

What does clause 6.3 of ISO 9001:2026 require?

Changes to the quality management system must be carried out in a planned manner, considering the purpose and consequences of the change, QMS integrity, resources, responsibilities and, new in 2026, communication, monitoring and review of results.

Is a change management procedure mandatory?

The standard does not mandate a documented procedure for 6.3. In practice a short procedure, a change request form and a log are an easy way to show that changes are planned and reviewed.

What kinds of change does clause 6.3 cover?

Changes to the QMS itself: new or changed processes, systems, sites, organization structure, key suppliers or scope. Design changes and production changes are controlled under clauses 8.3.6 and 8.5.6.

Is the ISO 9001:2026 transition itself a change under 6.3?

Yes, and it makes an ideal first record. Plan it, communicate it, monitor progress and review the results at management review.